# Phase 2 Decision Process

**Decision Point 1**

The Board acknowledges that, in line with the existing Phase 2 policy, the Secretariat may need to take more than 20 months to provide a Phase 2 recommendation to the Board. It therefore decides that in exceptional circumstances the Secretariat may extend, at no cost, the term of Phase 1 grant agreements by up to six months and decides that the Phase 2 Decision-Making Policies and Procedures document, as set out in Annex 6 to Board Document G/B10/8, shall be amended accordingly. The Secretariat shall inform the Board immediately upon taking action under this decision.

**Decision Point 2:**

The Board directs the Chair and Vice Chair of the Board to establish an ad-hoc task force to review the Phase 2 process and report back to the 11^th^ Board Meeting. The task force should be comprised of members of the Board, the Technical Review Panel, the Chair of the Technical Evaluation Reference Group and the Secretariat.